Ongoing Projects

Ongoing Projects of RVUN ( 2800 MW ) 

S.No

NAME OF UNIT

CAPACITY

COMMISSIONING TARGET

01.

Chhabra Supercritical Thermal Power Station Unit#5

660MW

Commissioning on 4.4.17

COD achieved on  9.8.2018

02.

                   Chhabra Supercritical Thermal Power Station Unit#6

      660 MW

 

Synchronised on Coal-1/12/18

COD achieved on  02.04.2019

03.

Suratgarh Supercritical Thermal Power Station Unit#7

660 MW

Synchronised on Coal-18/12/18

COD by Oct. 2019 

04.

Suratgarh Supercritical Thermal Power Station Unit#8

660 MW

Feb  2020