Works

Financial Year 2018-19

 

S.NO. EHV WORKS UNIT TOTAL EHV WORKS (COMMISSIONED)
TARGET ACHIEVEMENT DURING ACHIEVEMENT UPTO
 
Sept-18 Sept-18
[I] 765 kV WORKS        
(A) LINES Ckt. kM. 0 0 0
(B) SUB-STATIONS No. 0 0 0
(C) CAPACITY MVA 0 0 0
 
[II] 400 kV WORKS        
(A) LINES Ckt. kM. 740 49.430 250.675
(B) SUB-STATION No. 2 0 0
(C) CAPACITY MVA 1630 0 0
 
[III] 220 kV WORKS        
(A) LINES Ckt. kM. 310 17.934 23.42
(B) SUB-STATIONS No. 3 0 0
(C) CAPACITY MVA 640 0 0
 
[IV] 132 kV WORKS        
(A) LINES Ckt. kM. 317 0 228.73
(B) SUB-STATIONS No. 15 0 6
(c) CAPACITY MVA 375 0 150
 
[V] AUGMENTATIONS   1500    
  400kV MVA   0 0
  220kV MVA   0 1130
  132kV MVA   50 275
[VI] CAPACITORS MVAR 300 0 21.72
[VII] MISC WORK CKT KM 0 0 0